File #: 2019-0887    Version: 0 Name: Centennial Park Aquatic Center (CPAC) Railing Replacement (Reissue) - ITB 19-028 Award
Type: MOTION Status: PASSED
File created: 11/26/2019 In control: Board of Trustees
On agenda: 12/16/2019 Final action: 12/16/2019
Title: Centennial Park Aquatic Center (CPAC) Railing Replacement (Reissue) - ITB 19-028 Award
Attachments: 1. ITB 19-028 Responsiveness Check, 2. ITB 19-028, 3. ITB 19-028 Bid Tab, 4. Contract-Signed
Title
Centennial Park Aquatic Center (CPAC) Railing Replacement (Reissue) - ITB 19-028 Award


History
On October 9, 2019, the Village of Orland Park issued Invitation to Bid (ITB) 19-024 for the replacement of the staircase railings leading up to the zero-depth pool waterslide at the Centennial Park Aquatic Center (CPAC).

On the ITB closing date, October 24, 2019, only one (1) bid had been submitted. Staff requested approval from the Village Board on November 4, 2019, to reject the original ITB due to a lack of bidders and to re-issue the invitation to bid, which the Board approved.

On November 5, 2019, this project was reissued as ITB 19-028. In an effort to publicize the ITB to a wider audience, Parks staff reached out to contractors directly and Bid Net categories were expanded. In total, 291 contractors were notified of the ITB, four (4) downloaded the bid documents and one (1) bid was submitted by the November 19, 2019 closing date. The same contractor (Crossroads Construction of Lombard, IL) as the original ITB provided the sole submittal.

The ITB required bidders to provide four (4) bid alternatives based on materials and paint finishes outlined in the original bid specifications. Crossroad Construction’s submittal included an additional bid alternative for powder coated stainless steel. This option was the lowest cost of the five (5) proposed alternatives. A bid tabulation for Crossroads Construction is provided below:

Bid Tabulation - Crossroads Construction

Alternative 1 Galvanized Steel Paint 1 - $192,000
Alternative 2 Galvanized Steel Paint 2 - $192,000
Alternative 3 Stainless Steel Paint 1 - $178,400
Alternative 4 Stainless Steel Paint 2 - $178,400
Alternative Option Powder Coated Stainless Steel - $173,400

Specifications (Exhibit D - Special Provisions) in the ITB state that, “alternate paint systems must be approved by the Village.” As such, Parks staff consulted with CBBEL, who completed the bid specification for this project on behal...

Click here for full text