File #: 2020-0601    Version: 0 Name: 2019 Asphalt Pavement Maintenance - Contract Extension Request
Type: MOTION Status: PASSED
File created: 9/2/2020 In control: Board of Trustees
On agenda: 9/8/2020 Final action: 9/8/2020
Title: 2019 Asphalt Pavement Maintenance - Contract Extension Request
Attachments: 1. Contract - Signed
Title
2019 Asphalt Pavement Maintenance - Contract Extension Request

History
The annual Asphalt Pavement Maintenance project comprises the required maintenance upkeep for village facility parking lots, bike paths and also includes a large amount of asphalt roadway patching at various spot-locations throughout the Village. The parking lot maintenance includes patching, crack sealing, seal coating and striping as required per location. In May 2019, the project was bid out, five bids were submitted and the Village awarded a contract to the low bidder, M&J Asphalt Paving Company, Inc. (“MJAPC”) of Cicero, Illinois.

In 2019 and into 2020, the locations listed below for various maintenance activities were completed as described:

Parking Lots:
Discovery Park (Brook Hills) re-pave, add curbing
Cachey Park (Wheeler Drive) re-pave, add curbing + sidewalk+ path
Brentwood Park re-pave
Centennial Park Field 8 add path and bleacher pads
153rd Street Metra sidewalk extension for athletic fields
Orland Park Health & Fitness seal coat, re-stripe
Civic Center seal coat, re-stripe
Recreation Administration seal coat, re-stripe
Franklin Loebe Center seal coat, re-stripe

Paths:
Stellwagen Farm Path crack seal, seal coat
LaGrange Road (131st St. to 143rd St.) crack seal, seal coat
SW Hwy (Highwood Dr. to 179th St.) seal coat
104th Avenue (167th St. to 163rd Pl.) seal coat
Riviera Estates (88th Avenue S. of 143rd St.) existing path overlay
Helen Park & Field (Park Hill Subdivision) new path construction & dugout paving
Various Path Patch Locations over 60 patches

Various Street Patch Locations over 380 patches

MJAPC submitted a project cost of $615,923.25, which was below staff’s estimate of $699,399.00 for the scope of work. The collective budgeted amount for this project totals $775,000.00 and the original approval authorized the contract in a not-to-exceed amount ($615,923.25 bid amount plus a contingency of $159,076.7...

Click here for full text