File #: 2024-0134    Version: 0 Name: 2024 Asphalt Pavement Patching - ITB 24-024
Type: MOTION Status: PASSED
File created: 2/14/2024 In control: Board of Trustees
On agenda: 3/4/2024 Final action: 3/4/2024
Title: 2024 Asphalt Pavement Patching - ITB 24-024
Attachments: 1. ITB 24-024 - Audit Report, 2. ITB 24-024 - Bid Tabulation, 3. Proposal - Advantage Paving, 4. Proposal - D Construction, 5. Proposal - Lindahl, 6. Proposal - M&J Paving, 7. Proposal - M&J Underground, 8. Proposal - McGill
Title
2024 Asphalt Pavement Patching - ITB 24-024

History
The 2024 Asphalt Pavement Patching project comprises the required maintenance upkeep for a large amount of asphalt roadway patching at various spot-locations throughout the village.

For 2024, staff has been collecting asphalt patch locations throughout the Village to be provided for this work. The bid documents provided asphalt patch quantity estimates for the vendors to bid on.

ITB 24-024 for the 2024 Asphalt Pavement Patching project was published on the BidNet Direct website on January 24, 2024. BidNet data indicates one hundred forty-one (141) vendors were matched for this bid and eight (8) vendors downloaded all documents for the bid. On February 20, 2024 at 11:00am, six (6) sealed bids were opened by the Clerk’s Office for this project. The attached Bid Tabulation Sheet and Bid Responsiveness Sheet shows details of the bids for reference, and a summary of lump sum bid amounts is below:

D. Construction, Inc. of Coal City, Illinois - $250,000.00
Advantage Paving Solutions Inc. of Joliet, Illinois - $257,000.00
McGill Construction LLC of Frankfort, Illinois - $287,750.00
Lindahl Brothers, Inc. of Bensenville, Illinois - $301,300.00
M & J Asphalt Paving Company, Inc. of Cicero, Illinois - $309,950.00
M & J Underground, Inc. of Monee, Illinois - $326,200.01

D. Construction, Inc. of Coal City, Illinois is identified as the lowest responsible bidder for the 2024 Asphalt Pavement Patching project, with a submitted project cost of $250,000.00. This cost is below Public Works staff’s estimate of $281,000.00 for the anticipated project work areas. Therefore, it is staff's recommendation that D. Construction, Inc. of Coal City, Illinois be awarded the project for the 2024 Asphalt Pavement Patching project for $250,000.00. A contingency of $120,000.00, approximately 48% of the proposal total, is requested to address change orders made by additional work identified by staff for a total project cost of $370...